Top Dholera developers by months to their next declared completion date
Updated 17 November 2026. Compiled by the dholera.app desk from the sources listed at the end of this page.
13 of 22 promoter names on the GujRERA Dholera register still have a declared completion date ahead of 17 November 2026. The nearest is 30 April 2027, 5.4 months away, for GAP Associates and Pacificus Superinfra. The farthest next date is 30 April 2030. 9 names have every declared date already behind them. Read 17 November 2026. Builders and developers who still show a future date are listed by how many months remain to it.
- 5.4 monthsto the nearest declared date
- 13 of 22promoter names with a date ahead
- 30 Apr 2030farthest next declared date
Months to the next declared completion date, by developer
| Rank | Developer (promoter name on the record) | Next declared completion date | Months from 17 Nov 2026 | Project with that date | GujRERA number | Dates still ahead | Dates already passed |
|---|---|---|---|---|---|---|---|
| 1 | GAP Associates Private Limited | 30 April 2027 | 5.4 | GAP Industrial Park 1 | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA10173/EX1/030826/311226 | 1 | 0 |
| 2 | Pacificus Superinfra LLP | 30 April 2027 | 5.4 | Palm Greens Platinum 2 | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA09395/EX1/240326/311226 | 1 | 0 |
| 3 | Dholera Mega City 771 | 30 April 2028 | 17.4 | Dholera Megacity 771 | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA10217/200522 | 1 | 0 |
| 4 | Infinity Infracon (proprietorship) | 30 April 2028 | 17.4 | Dholera Megacity Iris | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA10133/020522 | 2 | 0 |
| 5 | Satyaja Infracon | 31 July 2028 | 20.5 | Bliss Grandeur- 1 | PR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PAA12734/030124/310328 | 2 | 0 |
| 6 | Satyaja Infratech | 31 July 2028 | 20.5 | Bliss 107 | PR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PAA12751/040124/310328 | 2 | 0 |
| 7 | GAP Studios LLP | 30 April 2029 | 29.4 | Aakar | PR/GJ/AHMEDABAD/DHOLERA/DSIRDA/RAA15713/190825/311228 | 1 | 0 |
| 8 | Parv Infracon LLP | 30 April 2029 | 29.4 | Shantiban Dreams | PR/GJ/AHMEDABAD/AHMEDABAD CITY/Dholera Special Investment Region Development Authority/MAA11736/A1M/281026/311228 | 1 | 0 |
| 9 | Shyam Infra | 31 March 2030 | 40.5 | Dholera Iconic | PR/GJ/AHMEDABAD/DHOLERA/DSIRDA/CAA16655/010426/310330 | 1 | 0 |
| 10 | Aaiji Infraspace(OPC) Private Limited | 30 April 2030 | 41.4 | Aaiji Residency 477 | PR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PAA15497/110725/311229 | 1 | 0 |
| 11 | Seksaria Buildcon LLP | 30 April 2030 | 41.4 | Shantiban Skylar | PR/GJ/AHMEDABAD/DHOLERA/DSIRDA/MAA16212/151225/311229 | 1 | 0 |
| 12 | Smart Dholera Housing Private Limited | 30 April 2030 | 41.4 | Piccadilly Square II | PR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PN36AA09936/210522 | 1 | 0 |
| 13 | Smarthomes Infrastructre Private Limited | 30 April 2030 | 41.4 | ABCD Enclave IV | PR/GJ/AHMEDABAD/DHANDHUKA/DSIRDA/PN70AA09970/080622 | 1 | 0 |
| - | Greenera Infrawell Private Limited | None ahead (latest was 30 September 2026) | - | Greenera Gardenvilla | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07425/EX1/EX2/220825/301225 | 0 | 4 |
| - | CT Corporation (Proprietorship) | None ahead (latest was 31 October 2025) | - | Dholera Marigold 548 | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07648/091120 | 0 | 1 |
| - | Chhabildas Developers Private Limited | None ahead (latest was 31 October 2025) | - | Dholera Sky | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07924/160121 | 0 | 1 |
| - | Aaiji Infra and Developers | None ahead (latest was 31 March 2025) | - | Aaiji Residency | PR/GJ/AHMEDABAD/DHANDHUKA/AUDA/PAA09145/111021 | 0 | 1 |
| - | Cube Infrastructure | None ahead (latest was 31 March 2025) | - | Nest 63 | PR/GJ/AHMEDABAD/AHMEDABAD CITY/Others/PAA10662/150922 | 0 | 1 |
| - | 7 Oak Developers | None ahead (latest was 31 December 2024) | - | 7 Oak Platinum 4 | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07741/051220 | 0 | 4 |
| - | 7 Oak Developers Private Limited | None ahead (latest was 31 December 2024) | - | Platinum 9 | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA10275/060622 | 0 | 1 |
| - | Fidato Buildcon | None ahead (latest was 31 December 2024) | - | Fidato Luxuria | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07658/101120 | 0 | 3 |
| - | Cube Infra | None ahead (latest was 31 March 2024) | - | Nest 29 | PR/GJ/AHMEDABAD/DHANDHUKA/AUDA/PAA07781/161220 | 0 | 1 |
Months = days between 17 November 2026 and the earliest declared completion date that is on or after that day, divided by 30.4. 13 promoter names have a date still ahead and are ranked soonest first; 9 names, whose every declared date is already behind 17 November 2026, are listed after them with a dash. Promoter names are as written on the records, so a company that registered under two spellings appears twice.
Download this table (CSV). Last checked 17 November 2026. Free to quote with a link to this page.
Promoters with no date ahead are not charted.
1. GAP Associates Private Limited
- Next declared completion date30 April 2027
- Months from 17 November 20265.4
- Project with that dateGAP Industrial Park 1
- GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA10173/EX1/030826/311226
- Projects with a date still ahead1 of 1
The register's next declared completion date for this promoter is 30 April 2027, about 5.4 months after 17 November 2026. A declared date is the promoter's own figure at registration, and GujRERA allows it to be extended, so treat it as the date to ask about, not a delivery guarantee.
2. Pacificus Superinfra LLP
- Next declared completion date30 April 2027
- Months from 17 November 20265.4
- Project with that datePalm Greens Platinum 2
- GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA09395/EX1/240326/311226
- Projects with a date still ahead1 of 1
The register's next declared completion date for this promoter is 30 April 2027, about 5.4 months after 17 November 2026. A declared date is the promoter's own figure at registration, and GujRERA allows it to be extended, so treat it as the date to ask about, not a delivery guarantee.
3. Dholera Mega City 771
- Next declared completion date30 April 2028
- Months from 17 November 202617.4
- Project with that dateDholera Megacity 771
- GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA10217/200522
- Projects with a date still ahead1 of 1
The register's next declared completion date for this promoter is 30 April 2028, about 17.4 months after 17 November 2026. A declared date is the promoter's own figure at registration, and GujRERA allows it to be extended, so treat it as the date to ask about, not a delivery guarantee.
4. Infinity Infracon (proprietorship)
- Next declared completion date30 April 2028
- Months from 17 November 202617.4
- Project with that dateDholera Megacity Iris
- GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA10133/020522
- Projects with a date still ahead2 of 2
The register's next declared completion date for this promoter is 30 April 2028, about 17.4 months after 17 November 2026. A declared date is the promoter's own figure at registration, and GujRERA allows it to be extended, so treat it as the date to ask about, not a delivery guarantee.
5. Satyaja Infracon
- Next declared completion date31 July 2028
- Months from 17 November 202620.5
- Project with that dateBliss Grandeur- 1
- GujRERA numberPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PAA12734/030124/310328
- Projects with a date still ahead2 of 2
The register's next declared completion date for this promoter is 31 July 2028, about 20.5 months after 17 November 2026. A declared date is the promoter's own figure at registration, and GujRERA allows it to be extended, so treat it as the date to ask about, not a delivery guarantee.
6. Satyaja Infratech
- Next declared completion date31 July 2028
- Months from 17 November 202620.5
- Project with that dateBliss 107
- GujRERA numberPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PAA12751/040124/310328
- Projects with a date still ahead2 of 2
The register's next declared completion date for this promoter is 31 July 2028, about 20.5 months after 17 November 2026. A declared date is the promoter's own figure at registration, and GujRERA allows it to be extended, so treat it as the date to ask about, not a delivery guarantee.
7. GAP Studios LLP
- Next declared completion date30 April 2029
- Months from 17 November 202629.4
- Project with that dateAakar
- GujRERA numberPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/RAA15713/190825/311228
- Projects with a date still ahead1 of 1
The register's next declared completion date for this promoter is 30 April 2029, about 29.4 months after 17 November 2026. A declared date is the promoter's own figure at registration, and GujRERA allows it to be extended, so treat it as the date to ask about, not a delivery guarantee.
8. Parv Infracon LLP
- Next declared completion date30 April 2029
- Months from 17 November 202629.4
- Project with that dateShantiban Dreams
- GujRERA numberPR/GJ/AHMEDABAD/AHMEDABAD CITY/Dholera Special Investment Region Development Authority/MAA11736/A1M/281026/311228
- Projects with a date still ahead1 of 1
The register's next declared completion date for this promoter is 30 April 2029, about 29.4 months after 17 November 2026. A declared date is the promoter's own figure at registration, and GujRERA allows it to be extended, so treat it as the date to ask about, not a delivery guarantee.
9. Shyam Infra
- Next declared completion date31 March 2030
- Months from 17 November 202640.5
- Project with that dateDholera Iconic
- GujRERA numberPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/CAA16655/010426/310330
- Projects with a date still ahead1 of 1
The register's next declared completion date for this promoter is 31 March 2030, about 40.5 months after 17 November 2026. A declared date is the promoter's own figure at registration, and GujRERA allows it to be extended, so treat it as the date to ask about, not a delivery guarantee.
10. Aaiji Infraspace(OPC) Private Limited
- Next declared completion date30 April 2030
- Months from 17 November 202641.4
- Project with that dateAaiji Residency 477
- GujRERA numberPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PAA15497/110725/311229
- Projects with a date still ahead1 of 1
The register's next declared completion date for this promoter is 30 April 2030, about 41.4 months after 17 November 2026. A declared date is the promoter's own figure at registration, and GujRERA allows it to be extended, so treat it as the date to ask about, not a delivery guarantee.
11. Seksaria Buildcon LLP
- Next declared completion date30 April 2030
- Months from 17 November 202641.4
- Project with that dateShantiban Skylar
- GujRERA numberPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/MAA16212/151225/311229
- Projects with a date still ahead1 of 1
The register's next declared completion date for this promoter is 30 April 2030, about 41.4 months after 17 November 2026. A declared date is the promoter's own figure at registration, and GujRERA allows it to be extended, so treat it as the date to ask about, not a delivery guarantee.
12. Smart Dholera Housing Private Limited
- Next declared completion date30 April 2030
- Months from 17 November 202641.4
- Project with that datePiccadilly Square II
- GujRERA numberPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PN36AA09936/210522
- Projects with a date still ahead1 of 1
The register's next declared completion date for this promoter is 30 April 2030, about 41.4 months after 17 November 2026. A declared date is the promoter's own figure at registration, and GujRERA allows it to be extended, so treat it as the date to ask about, not a delivery guarantee.
13. Smarthomes Infrastructre Private Limited
- Next declared completion date30 April 2030
- Months from 17 November 202641.4
- Project with that dateABCD Enclave IV
- GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/DSIRDA/PN70AA09970/080622
- Projects with a date still ahead1 of 1
The register's next declared completion date for this promoter is 30 April 2030, about 41.4 months after 17 November 2026. A declared date is the promoter's own figure at registration, and GujRERA allows it to be extended, so treat it as the date to ask about, not a delivery guarantee.
Who this list is for
It is for a buyer who has been told a project will be ready by a certain date and wants to compare that with the date on the regulator's record. The list turns each declared date into months from today, so two developers can be compared without counting on a calendar.
How the months are worked out
Take the days between 17 November 2026 and the declared date and divide by 30.4. For 30 April 2027 that is 164 days, which is 5.4 months. The same sum gives 41.4 months for 30 April 2030. To turn the months into other units, the unit converter handles areas, and the EMI calculator shows what a plot loan costs each month over the same period. For areas on the record, the converters for square metres, guntha and acres work from the same figures.
How to check a date yourself in five minutes
- Open gujrera.gujarat.gov.in, the official GujRERA site.
- Open the public project search and enter the registration number from the table, exactly as printed, including the slashes.
- Open the project record and compare the promoter name, the registration date and the declared completion date with this page.
- Open the quarterly progress reports for the project and note which quarters carry a filing.
- Ask the promoter in writing for the document you still need, then keep the reply with your booking papers.
Read the date on the record on the day you decide. The register allows a promoter to extend a date, so a date that is far ahead today may have moved by the time you pay.
What changed since August 2026
16 declared completion dates on the register moved later between the 4 August and 17 November 2026 reads, and none moved earlier. That is why this list is dated: the months are only as current as the read. Each move is shown as the register prints it:
- Aaiji Infraspace(OPC) Private Limited, Aaiji Residency 477: declared completion date on the register: 31 December 2029 in August, 30 April 2030 on 17 November.
- Dholera Mega City 771, Dholera Megacity 771: declared completion date on the register: 31 December 2027 in August, 30 April 2028 on 17 November.
- GAP Associates Private Limited, GAP Industrial Park 1: declared completion date on the register: 31 December 2026 in August, 30 April 2027 on 17 November.
- GAP Studios LLP, Aakar: declared completion date on the register: 31 December 2028 in August, 30 April 2029 on 17 November.
- Greenera Infrawell Private Limited, Greenera Gardenvilla 2: declared completion date on the register: 30 May 2026 in August, 30 September 2026 on 17 November.
- Pacificus Superinfra LLP, Palm Greens Platinum 2: declared completion date on the register: 31 December 2026 in August, 30 April 2027 on 17 November.
- Parv Infracon LLP, Shantiban Dreams: declared completion date on the register: 31 December 2028 in August, 30 April 2029 on 17 November.
- Infinity Infracon (proprietorship), Dholera Megacity Iris: declared completion date on the register: 31 December 2027 in August, 30 April 2028 on 17 November.
- Infinity Infracon (proprietorship), Park View: declared completion date on the register: 31 December 2027 in August, 30 April 2028 on 17 November.
- Satyaja Infracon, Bliss Grandeur- 1: declared completion date on the register: 31 March 2028 in August, 31 July 2028 on 17 November.
- Satyaja Infracon, Bliss Grandeur- 2: declared completion date on the register: 31 March 2028 in August, 31 July 2028 on 17 November.
- Satyaja Infratech, Bliss 107: declared completion date on the register: 31 March 2028 in August, 31 July 2028 on 17 November.
- Satyaja Infratech, Prelude Industrial Park: declared completion date on the register: 31 March 2028 in August, 31 July 2028 on 17 November.
- Seksaria Buildcon LLP, Shantiban Skylar: declared completion date on the register: 31 December 2029 in August, 30 April 2030 on 17 November.
- Smart Dholera Housing Private Limited, Piccadilly Square II: declared completion date on the register: 31 December 2029 in August, 30 April 2030 on 17 November.
- Smarthomes Infrastructre Private Limited, ABCD Enclave IV: declared completion date on the register: 31 December 2029 in August, 30 April 2030 on 17 November.
What this list cannot tell you
This list cannot tell you whether a project will be ready on its declared date, how much of it is built, or what any plot costs. It does a date sum on the register's figures and says nothing about delivery.
Questions people ask
How do I count the months to a RERA completion date?
Count the days from today to the declared date and divide by 30.4. For example, 17 November 2026 to 30 April 2027 is 164 days, which is 5.4 months. Use the date on the GujRERA record for your project, read on the day you decide.
Which Dholera developer has the nearest declared completion date?
GAP Associates Private Limited and Pacificus Superinfra LLP, both with 30 April 2027, about 5.4 months after 17 November 2026. Both registration numbers carry an EX1 marker, which shows an extension was sought. The table prints both numbers.
What if a declared completion date has already passed?
The record keeps the date the promoter declared. 9 promoter names have every declared date behind them. Ask the promoter for the completion certificate or an extension order, and read the latest quarterly progress report for the project.
Can the completion date on the register change?
Yes. 16 dates moved later between 4 August and 17 November 2026. A promoter may apply for an extension, and the registration number then carries an EX marker. Read the date again before you sign an agreement.
Is a date on RERA a delivery promise?
It is the date the promoter declared when registering. It is the date to ask about. GujRERA publishes it, and the record does not show progress by itself.
Read next
- Unit converter for Dholera land areas
- Dholera plot loan EMI calculator
- Dholera builders
- Best Dholera calculators and tools
- Square metre converter
Sources
- GujRERA public project register (read 17 November 2026)
- GujRERA project record, example (7 Oak Platinum 4, record 10840) (read 17 November 2026)
- Dholera SIR, DSIRDA and DICDL official portal (checked 17 November 2026)
- GujRERA quarterly progress reports, example project record 10840 (read 17 November 2026)