What is actually built at Dholera

Each mega-project with its honest status and dated milestones. Progress bars appear only where a percentage has a source. Announcements live on their own shelf, because an MoU is not a building.

Updated 3 August 2026 · facts verified to 27 July 2026 · tags: Durable Reported Target

Ahmedabad-Dholera Expressway

Open

109 km four-lane greenfield access-controlled expressway (expandable to eight lanes), design speed 120 km/h, built by NHAI. Travel time from Ahmedabad reported cut from over two hours to roughly 40 minutes to one hour.

  • 31 Mar 2026Reported inaugurated by the Prime Minister and operational. reported
  • 2026Toll collection via FASTag planned. Specific rates are not reliably sourced yet. target

Dholera International Airport

Under construction

Greenfield airport about 20 km from the SIR core and 80 km from Ahmedabad. Single 3,200 m Code 4E runway in Phase 1. SPV: DIACL (AAI 51%, Gujarat 33%, NICDC 16%).

Reported ~80% complete, Jul 2026 ministerial review
  • 4 Jun 2026First aircraft landing: an AAI calibration flight (VT-CNS) touched down on the completed runway. A trial, not an opening. reported
  • Jul 2026Runway, taxiways and ATC tower reported complete; passenger terminal about 75%. Overall reported near 80%. reported
  • Sep-Oct 2026Operations target after the Civil Aviation Minister's review. This date has slipped before; treat as a target. target

Tata semiconductor fab

Under construction

Rs 91,000 crore fab by Tata Electronics with PSMC. Capacity up to 50,000 wafers per month on 300 mm; mature nodes first (90 nm and 55 nm, then 28 nm). Union Cabinet approved 29 Feb 2024.

Civil works reported past halfway, Apr-May 2026
  • 29 Feb 2024Union Cabinet approval under the India Semiconductor Mission. durable
  • 17 May 2026Lithography partnership with ASML confirmed on Tata Electronics' own press page. durable
  • ~Apr 2026A 66-hectare Tata Semiconductor SEZ notified at Dholera. reported
  • Dec 2026First-silicon trial production target stated by the minister and the CEO. target
  • Mid 2028Commercial production reportedly pushed to mid 2028. reported

Dholera Ultra-Mega Solar Park

Partly operational

About 300 MW is commissioned, including Tata Power's 300 MW single-axis tracker plant across 1,320 acres. Phase-I sanction is 1,000 MW under GPCL; the long-range announced target is 5,000 MW by around 2030.

300 MW commissioned of the 1,000 MW sanctioned Phase-I (CEA, Sept 2025)
  • Sept 2025CEA quarterly report: 300 MW commissioned, 700 MW under development targeted for Mar 2027. durable
  • ~20305,000 MW ultimate target. A target, not capacity. target

Ahmedabad-Dholera semi-high-speed rail

Approved

About 134 km double line connecting Ahmedabad, the SIR, the airport and Lothal NHMC, cleared by the CCEA at roughly Rs 20,667 crore. Billed as India's first semi-high-speed rail on indigenous technology.

  • 13 May 2026CCEA approval confirmed via PIB release 2260624. durable
  • 2030-31Completion target on PM Gati Shakti. The often-quoted 220 km/h speed is press reporting, not in the PIB release. target

Watchlist: announced and MoU-stage

Announced

Big names at agreement or exploration stage. Announcements are momentum, not construction, so they sit on a separate shelf here.

  • 20 Feb 2026L&T and Vyoma AI data centre agreement, Rs 25,000 crore for 250 MW green AI-ready capacity, operations targeted around 2028. reported
  • 5 May 2026Union Cabinet cleared two further semiconductor units (one at Dholera, one at Surat), together above Rs 3,900 crore. reported
  • 30 Jun 2026Fujifilm India MoU to explore a semiconductor-materials base at Dholera. Exploratory. reported
  • Jul 2026Embraer and Adani MoU exploring a civil-aircraft assembly line at the airport, targeted around 2028, site not final. reported
Reading this page: Dholera's documented history includes real anchors and real slippage in the same decade. Both belong on the record. When a date here is a target, it is written as a target, and it stays that way until something verifiable happens.

Tracker questions

When will Dholera airport open?

Operations are targeted for September or October 2026 after a July 2026 ministerial review reported the airport around 80 percent complete. The first trial landing happened on 4 June 2026. Opening dates for this airport have slipped repeatedly since around 2010, so treat every date as a target until DIACL announces commercial operations.

Is the Dholera expressway open?

Yes, as reported. The 109 km Ahmedabad-Dholera Expressway was reported inaugurated on 31 March 2026 and operational, cutting the drive to roughly 40 minutes to one hour.

Has the Tata fab produced a chip yet?

No source confirms a chip produced as of late July 2026. Civil work is reported past halfway, first-silicon trial production is targeted for December 2026, and commercial production is reportedly planned for mid 2028 starting on mature nodes.